AERC fixes threshold for any intrastate transmission projects as per Tariff policy 2016

Jan 13, 2022 | by TeamLease RegTech Legal Research Team

Loading audio.....

Industry Specific ComplianceThe Assam Electricity Regulatory commission (AERC) on January 12, 2022 has issued a notification for fixation of the threshold limit of Rs 100Cr, irrespective of the voltage level for all new development and augmentation schemes of Intra State transmission projects.

All new and augmentation of intra State transmission projects shall be developed through Tariff Based Competitive Bidding (TBCB) in accordance with the guidelines issued by the State Transmission Utility (STU).