Industry Specific ComplianceThe Government of Rajasthan on August 16, 2023, issued a notification regarding the Installation of Solar Meters in case of a Net Metering connection 

The following has been stated namely: -

• It states that All meters installed at the Renewable Energy generating system shall comply with the CEA (Installation and Operation of Meters) Regulations, 2006, and subsequent amendments thereof

• It further states that the CT-operated solar meter shall be installed above 1 8.65 KW solar plant capacity under the Net Metering arrangement. 

 

[Notification No.AVVN/CE(HQ)/SE(C)XEN(C-II)/F./2023-24/D.1397]