Draft Dadra and Nagar Haveli Land Reforms Rules, 2024 (as extended to the Daman and Diu)

Jan 28, 2024 | by TeamLease RegTech Legal Research Team

Free Legal updates for the week 00


Commercial ComplianceThe Government of Dadra and Nagar Haveli on January 22, 2024, issued the Draft Dadra and Nagar Haveli Land Reforms Rules, 2024 (as extended to the Daman and Diu).

The following provisions have been stated:

• Statement under section 11, which states “Future Acquisition”

(1) The statement to be filled, under sub-section (2) of section 11 shall be in Form I.

(2) The statement shall be filed before the Prescribed Authority in duplicate together with a certified copy of the document evidencing the transfer.

(3) The particulars furnished in the statement shall be entered in a register to be maintained in Form II and one copy of the statement shall be returned by the Prescribed Authorities after indicating thereon the serial number under which the statement is so registered and putting thereon his signature with date.

(4) The particulars of action taken on the statement shall be indicated in the relevant column of the register.

• Determination of value of building or structure under section 14(2), which states “Compensation for lands in excess of the ceiling area”

(1) The determination of the value of a building or other structure referred to in sub-section 2 of section 14 will be done by the Public Works Department Daman and Diu in a similar manner as followed in the land acquisition proceeding projects.

Objections and suggestions to the Draft Dadra and Nagar Haveli Land Reforms Rules, 2024 (as extended to the Daman and Diu), will be considered by the Government within 15 days from January 22, 2024, and may be sent in writing to the office of the Collector, Collectorate, Daman.

[Notification No 2/COL/LND/LNDReformsRules/40/2023-24/165]