The Madhya Pradesh Electricity Regulatory Commission (MPERC) on January 17, 2024, issued the Draft Madhya Pradesh Electricity Regulatory Commission (Power Purchase and Other Matters with respect to conventional fuel-based Captive Power Plants) Regulations, (Revision-I) 2009 (Second Amendment) {RG-30 (I) (ii) of 2024}, to further amend the Madhya Pradesh Electricity Regulatory Commission (Power Purchase and other matters with respect to Conventional Fuel Based Captive Power Plants) Regulations 2009 [RG 30 (I) of 2009].
The following regulations have been stated:
• Regulation 4.15, which states “Charges for Stand-by support”, shall be amended as follows:
“words and digits “Rs. 31” and “Rs. 25” appearing in regulation 4.15 shall be substituted by “Rs. 16” and “Rs. 13” respectively.
• In Regulation 4.15, which states “Charges for Stand-by support”, the 2nd proviso shall be substituted by the following proviso, namely:
“Provided further that the commitment charges as extended vide order dated December 14, 2023, shall be applicable up to the date of commencement of this amendment and the revised commitment charges indicated above shall be applicable till March 31, 2027 and shall be reviewed thereafter.”
The Suggestions/Objections/Comments on the above draft Regulation will be considered by the Commission and may be sent to the Secretary, Madhya Pradesh Electricity Regulatory Commission, 5th Floor, "Metro Plaza", Bittan Market, E-5 Arera Colony, Bhopal - 462016 to reach the Commission latest by February 08, 2024.
The Suggestions/Objections/Comments may also be submitted by e-mail to [email protected] & [email protected] or by fax to phone no. 0755-4004137.
[Notification No MPERC/D(L&R)/2024/181]