The Kerala Real Estate Regulatory Authority (K-RERA) on April 29, 2024, imposed the penalty for promoters who fail to submit Quarterly Progress Reports.
The following has been stated:
• Rs. 50,000/- in case of real estate projects with estimated costs exceeding Rs.100 crores.
• Rs. 25,000/- to the promoters of real estate projects with estimated cost exceeding Rs. 50 Crores to Rs. 100 Crores.
• Rs. 10,000/- to the promoters of real estate projects with an estimated cost of less than Rs. 50 Crores.
[Notification No K-RERA/T3/102/2023]