Andhra Pradesh Electricity Regulatory Commission (Threshold Limit for the Development of Inter-State Transmission Projects under Tarrif Based Competitive Bidding) Regulation 2024

May 20, 2024 | by TeamLease RegTech Legal Research Team

Free Legal updates for the week 00


Industry Specific ComplianceThe Andhra Pradesh Electricity Regulatory Commission (APERC) on May 17, 2024, issued the Andhra Pradesh Electricity Regulatory Commission (Threshold Limit for the Development of Inter-State Transmission Projects under Tariff Based Competitive Bidding) Regulation 2024.

This shall come into force on May 17, 2024.

The following has been stated namely: -

• It states that the commission shall fix the threshold limit of above rupees two hundred and fifty crores excluding land cost for the new Intra-State Transmission (InST) projects to be awarded under TBCB, and it shall be implemented by the bid process coordinators.

• It states that the entire Intra-State Independent Transmission projects including an upstream/downstream project shall be designed as a single project for inviting bids for the development of the project through TBCB.

• It states that if the STU intends to implement any InST above or below the threshold limit, due to some specific reasons such as the project being of a critical nature, the STU shall implement such projects through Tariff based Competitive Bidding with the prior approval of the commission for the same.

[Notification no. - APERC/Secy/F.No.S-19(Vol-III)/D.No.1036]