The Central Electricity Authority (CEA) on February 12, 2025, issued Procedure For Verification Of Captive Status Of Such Generating Plant, Where Captive Generating Plant And Its Captive User(S) Are Located In More Than One State with the approval of the Central Government.
The objective of this procedure is to verify the captive status of such generating plants by the Central Electricity Authority where Captive Generating Plant (CGP) and its User(s) are located in more than one State, as per the requirements of Rule 3 of the Electricity Rules, 2005.
This procedure shall be applicable for all power plants and consumers, who desire to submit their claim for verification as CGP and associated Captive User(s) to the Authority in accordance with sub-rule (3) of Rule 3 of the Electricity Rules, 2005.
This procedure shall be applicable from FY 2024-25.
Please find the detailed procedure in the document below.
[Order No. 10/2025]